JTL
مركز القيادة التنفيذي للمشروع

لوحة الأداء التنفيذي والقيمة المكتسبة — JTL

تاريخ بيانات المصدر: Apr / May-2026
حالة التقرير: مؤقت — يتطلب التحققCurrent Aug-2026 PV, EV and AC were not present. EVM stays locked until same-date verified inputs are entered.
Historical source snapshot

Executive position at latest available file dates

Not a current Aug-2026 status

Contract Value
413.52 SAR M

Commercial basis · Mod BOQ-2

Cost Budget
347.18 SAR M

Budget total · May-2026

Actual Cost
228.93 SAR M

Recorded actual · May-2026

Physical Progress
63.27 %

Reported actual · May-2026

Schedule SPI
0.914

P6 R7 · Data Date 30-Apr-2026

Accepted Test Length
11.42 km

Testing file · date not stated

Workstream readiness

Progress profile

Source-specific definitions

Physical progressMay-2026 budget dashboard
63.3%
Billing / ContractIPC #35 · Apr-2026
56.2%
Pipeline executed28,245 / 38,012 m
74.3%
Accepted test sections11,421.84 / 38,012 m
30.1%
Valve chambers108 / 182 chambers
59.3%
Asphalt reinstatement3,796 / ~26,000 m²
14.6%
Executive attention

Immediate decision queue

4 open controls

01
Confirm EVM source values

Planning + Cost Control · Before issue

BLOCKER
02
Resolve unbilled revenue mismatch

QS / Commercial · Before issue

RECONCILE
03
Confirm current schedule Data Date

Planning · Before issue

VERIFY
04
Reconcile equipment population

Plant / Admin · Before issue

RECONCILE
Financial exposure

Top identified risk exposure

SAR million · historical registers

Data governance

Source confidence

No silent assumptions

52/100
Partial — historical inputs only

Commercial and cost totals are available; EVM period alignment is incomplete.

Contract value supportedVerified
May-2026 actual cost supportedVerified
PV / EV for 31-Aug-2026Missing
Current AC for same Data DateMissing